claims

This month, I’m going to take the opportunity to blow our own trumpet a little…

And why not?

HDP has worked with a number of clients on extension of time claims connected with COVID-19 recently. Of particular note, we helped clients on two complicated and high-value projects with very high levels of delay penalties. I’m really proud of the way our team manages these projects to achieve successful outcomes. So by sharing the details as case studies, I hope it offers some food for thought for managing your own claims…

The Projects

Both projects were EPC contracts undertaken by overseas contractors to engineer, procure and construct industrial plants. Both included many materials and significant quantities of plant and equipment which were manufactured overseas.

In a more conventional extension of time claim, the activities affected by the claimable delay generally only amount to a small number. They may be relatively easily impacted into a suitable programme to demonstrate the effects of the claimable delay on the time for completion. An extension of time claim related to  variation, for example, would require a fragnet to be created to show the instruction, shop drawing preparation and approval, material submission and approval, procurement, delivery and site installation. Other claims may include several delay events with corresponding periods of delay being impacted into a programme. If the logic links are correct, the programming software will produce the information necessary to calculate the extension of time due to the event or events.

Not Your Usual EoT Claim

Delays related to COVID-19 were, however, just like COVID-19 itself, very, very different. On the projects in question, COVID-19 delayed literally hundreds of the programmed activities. Overseas manufacture and delivery of many items was delayed because of lockdowns. Travel restrictions meant that our clients could not mobilise personnel for site installation and specialist personnel for testing and commissioning. The countries in which the projects were based were placed under lockdown. The sites were closed due to COVID-19 amongst the project personnel and social distancing in the workplace reduced productivity. In addition to delays incurred by our clients, local subcontractors were similarly affected by many of these matters. This list of delays, all due to COVID-19, went on and on.

Thinking Outside the Box

This unprecedented situation called for us to re-think the conventional approach to extension of time claims. Especially the delay analyses necessary to prove the effect of COVID-19 on the time for completion. The fact that we did so, and did so successfully for our clients, was validated because the claims were accepted by both the Engineer and the Employer and our clients received the required extension of time awards on both projects. What’s more, the claims were not subject to any requests for further particulars and there was agreement within weeks of submission. That’s what we call a successful outcome.

Hewitt Decipher Partnership’s expert consultants have been preparing and responding to claims for many years. We know how to think out of the box when required to do so and how to formulate the best strategy for a successful outcome for our clients. Can we help you with COVID-19 related claims? Get in touch.