Case Studies > Programming and Planning > Case Study 2
New Football Stadium, UK
Assisting specialist subcontractor in determining their programme
Our Brief
We were asked by a specialist contractor to provide support with determining a programme which represented their scope of work and required resources on a project. The project was running behind programme and the Employer was alleging that the delays were due to lack of performance.
The Services
We provided a site-based planner who attended site on weekly basis and effectively became part of the subcontractor’s team.
The Benefit
Our planning services ensured that a robust programme was developed to support the Sub-contractor’s entitlement to additional time for delays. This enabled the subcontractor to defend against liquidated damages.